Largest wind farm on Skye faces fresh obstacle despite fewer turbines

Councillors have previously objected to the proposed wind farm citing concern over landscape and cumulative environmental impact.

placeholder image
Supplied

Highland councillors have again raised an objection again to plans for what could become the Isle of Skye’s largest wind farm.

The proposed Glen Ullinish II development, by Muirhall Energy, will be considered by the Highland Council’s North Planning Applications Committee on Wednesday.

Councillors previously voted unanimously to object to the original proposal for 47 turbines, each up to 200 metres high, citing concerns over landscape, visual and cumulative environmental impacts. A revised application has since reduced the number of turbines to 33, with the council still holding its objection.

Muirhall Energy said the latest plans had been shaped by feedback from the local community and other stakeholders. The company said it had moved the turbines, planned for near Struan, between Portree an d Dunvegan in the northwest of Skye, further from homes, prominent viewpoints and protected natural areas. It said the revised design would also reduce the number requiring aviation lighting and help minimise impacts on local birdlife, including eagles, by moving turbines away from areas they are known to frequent.

However, the Skye Wind Farm Information Group (SWIG), a community organisation comprising island residents and local business owners, believes the revised scheme would still have a profound impact on the island’s landscape, wildlife, economy and communities.

In its submission ahead of next week’s meeting, SWIG described the 33-turbine development, which also includes battery storage and substations, as a project of enormous scale in a landscape internationally renowned for its natural beauty.

The group warned that the turbines would be visible from numerous well-known beauty spots and historic landmarks, including views of Dunvegan Castle and Gardens, and argued that the development could damage an economy heavily dependent on tourism.

SWIG also questioned the need for the project, arguing that Skye already generates substantially more electricity than it consumes and claimed that Scotland is on course to meet its renewable energy targets through wind farm developments already approved or under construction. Targets, however, remain a mixed picture due to grid infrastructure delays and planning bottlenecks.

Transport is another major concern for islanders. The group estimates that at least 100 convoys of abnormal loads would be required to transport equipment more than 41 miles from Kyle of Lochalsh to the site in north-west Skye. Turbine blades could be up to 81 metres long, potentially requiring road closures, the removal of safety barriers and traffic lights, and the blasting of rock faces to allow the vehicles to pass.

SWIG said that the project’s environmental impact assessment has not adequately examined the consequences for residents, businesses, emergency services, visitors and the tourism sector, or the cumulative disruption from construction traffic associated with other proposed wind farms on the island.

The group has also questioned the proposed transport arrangements, claiming that Muirhall representatives told local community councils that Kyle Harbour was no longer a viable option for unloading the turbine blades because of restrictions on space and access. However, the revised application continues to identify the harbour as the intended unloading point.

Muirhall Energy has been contacted for comment

The proposals for Glen Ullinish II, which would generate 217.8 MW, replace the company’s already approved application for an 11-turbine Glen Ullinish Wind Farm to “further maximise the project’s contribution to Scotland’s climate change targets,” according to Muirhall.

Comments

 0 comments

Want to join the conversation? Please or to comment on this article.

Dare to be Honest
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice