Further rail disruption during Edinburgh-Glasgow rail upgrade

PASSENGERS face five more months of disruption during the upgrading of the main Edinburgh-Glasgow rail line.

This article contains affiliate links. We may earn a small commission on items purchased through this article, but that does not affect our editorial judgement.

Passengers face further delays on Edinburgh -Glasgow route. Picture: John DevlinPassengers face further delays on Edinburgh -Glasgow route. Picture: John Devlin
Passengers face further delays on Edinburgh -Glasgow route. Picture: John Devlin

Trains will be replaced by buses after around 8.30pm between Sundays and Thursdays from 4 September to 8 December, and 8 January to 31 March.

Services on some lines which use part of the route will also start later on Sundays - around 11am.

Read More
Edinburgh-Glasgow trains every ten minutes

These include Perth-Dunblane-Stirling-Edinburgh trains.

Hide Ad
Hide Ad

The £742 million electrification project – the Edinburgh Glasgow Improvement Programme – is already running seven months behind schedule, with electric trains not now expected to start running until next July.

The Alliance warned there would be further disruption to follow, including on other routes.