Edinburgh-Glasgow rail electrification delayed again

Plans to speed up journeys by electrifying the main Edinburgh-Glasgow rail line have been delayed again, transport minister Humza Yousaf told MSPs today.
A faulty component as part of the overhead power lines is likely to have to be replaced. Picture: Network RailA faulty component as part of the overhead power lines is likely to have to be replaced. Picture: Network Rail
A faulty component as part of the overhead power lines is likely to have to be replaced. Picture: Network Rail

He announced Network Rail had said a "safety-critical" component had failed, which would affect the planned start of electric trains in July.

The setback follows the original completion date being put back from last December because of other difficulties with the project.

Hide Ad
Hide Ad

The problem will delay overhead electric power cables going live at the end of this month.

The "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network RailThe "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network Rail
The "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network Rail

That will have a knock-on effect on ScotRail drivers being trained to drive electric trains on Scotland's busiest route.

Industry sources told The Scotsman that the latest problem could also postpone the start of an all-electric service of brand new trains on the line from December.

It is understand the faulty equipment is part of the overhead power lines and will have to be replaced - possibly over the full length of the 46-mile route.

Mr Yousaf said any further delay after the earlier problems announced last summer would be "extremely disappointing".

The project to speed up journeys was originally due to have been completed last December. Picture: Network RailThe project to speed up journeys was originally due to have been completed last December. Picture: Network Rail
The project to speed up journeys was originally due to have been completed last December. Picture: Network Rail

The £742 million project will enable faster-accelerating, longer and greener electric trains to replace diesels on the route via Falkirk High.

Electric trains from other routes are planned to initially take over some services by the end of July.

They were due to be followed by the first of a fleet of brand-new Japanese Hitachi trains from September, with the last diesel trains replaced in December.

Hide Ad
Hide Ad

They will be progressively lengthened between December and the end of next year, when Edinburgh to Glasgow journeys are due to be cut by about ten minutes to 42 minutes.

The "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network RailThe "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network Rail
The "energisation" date of the overhead power lines at the end of May will be put back because of the problem. Picture: Network Rail

Mr Yousaf said the delay further highlighted the need for the devolution of control over Network Rail so the Scottish Parliament could properly hold it to account over its projects and spending north of the Border.

The news came in a letter from Network Rail chief executive Mark Carne.

A Network Rail spokesman said: “There is an emerging issue around some of the installations on the Edinburgh-Glasgow electrification programme.

"We are working hard to assess the implications of this and won’t be commenting further until we have completed that work.”