Queensferry Crossing: Nicola Sturgeon under fire over `snagging'

Nicola Sturgeon has said every effort would be made to minimise inconvenience on the Queensferry Crossing as she faced a barrage of criticism over lane closures on the new bridge.

This article contains affiliate links. We may earn a small commission on items purchased through this article, but that does not affect our editorial judgement.

At First Minister’s Questions, Ms Sturgeon was attacked over the revelation that the £1.35 billion bridge will be partially closed for surfacing work until Thursday.

Transport officials said more lane restrictions could be expected on the crossing over the next 10 months due to ‘’snagging’’ issues, which Ms Sturgeon likened to the problems encountered when moving into a new house.

Hide Ad
Hide Ad

Nicola Sturgeon said the work beginning on Thursday was “the only identified work” requiring peak-time lane closures.

Nicola SturgeonNicola Sturgeon
Nicola Sturgeon
Read More
Queensferry Crossing to have 10 months of lane restrictions

At Holyrood, Ms Sturgeon came under attack from Scottish Conservative leader Ruth Davidson, who claimed ministers had failed to come clean about the problems affecting the bridge.

Ms Sturgeon said the work beginning this evening was “the only identified work” requiring peak-time lane closures.

“The work that will start tonight is the only identified snagging work that will require peak-time lane closures. Any future lane closures that can’t be avoided will be at night, not during the day, and not during peak hours.

Nicola SturgeonNicola Sturgeon
Nicola Sturgeon

“Under the contract all snagging works are carried out at no additional cost to the Scottish Government.”

Work is scheduled to begin at 10pm tonight and finish by 6am on Wednesday December 6.

During that time, southbound traffic heading towards Edinburgh will use the Forth Road Bridge, while northbound traffic will use the Queensferry Crossing.

Earlier this week Transport Scotland told a Holyrood committee that issues with road surfacing were known about in August - before the crossing’s opening - but a solution was not found until a ‘’couple of weeks’’ ago.

Hide Ad
Hide Ad

Ms Sturgeon said: “When the solution to this particular piece of work was agreed ministers were told - that happened on Tuesday of last week.

“As soon as there was then confirmation from the Met Office about the weather window - that happened on Monday this week - Parliament and the wider public were informed.

“In other words, there was no delay, things happened completely timeously.”

Ms Sturgeon went on to compare the problems with the “snagging” experienced when new owners move into a house.

“Anybody who has ever moved into a new house knows that snagging is required on construction projects. There is snagging work to be done. The project director told Parliament in June that there would be a period of three to six months of snagging work. That is being carried out.”

Scottish Conservative leader Ruth Davidson accused the government of “dripping out information” on the bridge works.

She said: “Transport Scotland knew that the road over the bridge was faulty when the bridge was opened back in August, because that’s what they said in Parliament yesterday, yet the Transport Minister said this morning that he knew nothing about the partial closure until last week.

“What jars here is the way that they pushed through the opening of this bridge in the summer and claimed it as a symbol of SNP competence, but now there’s a problem it’s ‘don’t look at us we’re just the Scottish Government’.

Hide Ad
Hide Ad

“In September it was jobs done and pats on the back all round, but on Monday we were told there would be another five days of work needed and yesterday those five days became another 10 months of possible disruption.

“It’s the dripping out of this information rather than simply levelling with people that’s damaging the public’s trust.”

Scottish Liberal Democrat leader Willie Rennie said: “Who spends over a billion pounds on a bridge then closes it weeks later?

He added: “With work predicted to last until September next year the completion of this crossing will be two years late. People deserve openness at last from this government.

“This government’s priority has been to not disrupt the ceremony with troublesome facts.”