10,000 tonnes of concrete removed from Queen Street tunnel

Concrete being removed during track upgrading of the Queen Street tunnel in Glasgow would cover the new pitch at Hampden, Network Rail has revealed.
Network Rail staff at work on a project to upgrade Queen Street tunnel. Picture: SNS GroupNetwork Rail staff at work on a project to upgrade Queen Street tunnel. Picture: SNS Group
Network Rail staff at work on a project to upgrade Queen Street tunnel. Picture: SNS Group

The first of the 10,000 tonnes lying under the twin tracks has just been excavated as part of the five-month project.

The £70 million scheme is also the most expensive of its type over that timescale, involving 450 engineers working round the clock in three shifts.

Hide Ad
Hide Ad

Programme director Rodger Querns said it remained on schedule to be completed on 8 August.

Track in the mile-long tunnel which is up to 40 years old will be replaced, and lowered to provide space to power new electric trains.

Platforms on the main concourse are being lengthened and realigned in the first part of a major revamp of the station.

Trains are being diverted to below-ground platforms or Glasgow Central.