Design engineers warned of 'concern' over Holyrood changes
CONSTRUCTION chiefs at the Scottish Parliament building were warned six years ago that beams in the building's roof were a major "concern" following last-minute alterations, made to make the chamber look more attractive.
Documents handed to the Holyrood inquiry reveal a two-year tug-of-war between engineers, architects and builders over the roof, and specifically the 60 enormous timber trusses which span the cavernous chamber.
The Parliament is still in limbo this weekend after one of the beams sprang loose from its socket on Thursday, dangling precariously over the heads of MSPs below. Engineers are working throughout the weekend to remedy the problem but Parliament chiefs are already making arrangements for MSPs to sit elsewhere this week, piling on the embarrassment.
The documents show how the roof's engineers, Ove Arup, became increasingly concerned about its structure from 2000 to 2002 as they discovered that alterations were being made to their original plans.
In one letter to the Parliament's architects, RMJM, dated November 30, 2000, Ove Arup director David Lewis explicitly writes of his worries over changes to the "nodes" in the roof - the 112 metal sockets in which the beams are held.
"There are two issues regarding the design of the debating chamber which are concerning me greatly," he wrote. "They are the design of the nodes for the roof trusses and the mast sizes."
He added: "We have been discussing information for several weeks with you now, attempting to find solutions which satisfy the structural and aesthetic requirements of the design. Clearly there have been, and still are, considerable conflicts here with your difficulty in accepting the necessary structural dimensions to enable the members and sections to work."
Giving evidence to the Holyrood inquiry two years ago, Lewis said these issues had been "resolved" as they went along.
However, two years later, the documentation shows that the architects and engineers were still in conflict over changes to the roof the architects wanted to make in order to add to its aesthetic appeal.
There is no evidence yet as to the cause of last week's events, with theories yesterday even suggesting the wooden beams may have shrunk since being installed.
Engineers from the company working on the building are expected to issue a report tomorrow to the Presiding Officer on the reasons for the collapse.
- Rangers takeover: Duff & Phelps threaten legal action against BBC
- Today’s youth not fit to be employed, says car firm Arnold Clark
- Family mourn death of Glasgow ‘fight’ schoolboy
- Rangers administration: Fans fear Duff & Phelps claims could scare off Green
- Rangers takeover: triple penalty punishment enough, says Johnston
- Alistair Darling leads ‘No to independence’ fight over tea and biscuits
- Scottish independence: SNP flip-flops over Nato
- Scottish Independence: SNP ‘won’t be Yes campaign’s only voice’
- Today’s youth not fit to be employed, says car firm Arnold Clark
- Scottish independence: ‘People here are best qualified to run Scotland’
Looking for...
Featured advertisers
Jobs
Search for a job
Motors
Search for a car
Property
Search for a house
Weather for Edinburgh
Friday 25 May 2012
Today
Sunny spells
Temperature: 9 C to 20 C
Wind Speed: 15 mph
Wind direction: East
Tomorrow
Sunny
Temperature: 8 C to 20 C
Wind Speed: 16 mph
Wind direction: North east