Cash row puts tram contract at risk
A MULTI-million-pound contract for Edinburgh's tram works could be torn up if the company in charge of it refuses to drop demands for an extra £80m.
As parts of Edinburgh continue to suffer gridlock because of road closures, council sources suggested they were ready to bring in a new company to finish the work if the current contractors – German construction company Bilfinger Berger – refuses to do so within the agreed budget of 512m.
But with negotiations between the parties remaining deadlocked, fears were raised that the whole project was now facing delays of a year or longer, to the anger of Edinburgh traders and residents.
Politicians and retailers accused the company of "holding the city to ransom", and urged the council to stick to the original cost and timetable of the four-year-long works.
Bilfinger Berger agreed to the 512m contract in May last year, but last week said it needed an extra 40m to 80m to complete the works.
The demand came on Thursday, 48 hours before Edinburgh's Princes Street was closed for a scheduled nine months for the tram rails to be laid.
The company claimed it needed the extra money because of expensive delays to tram works at Leith Walk and Gogarburn, caused by utilities companies failing to lay cables and pipes on time.
The closure of Princes Street went ahead as planned on Friday, but without any construction workers, as the two sides failed to reach agreement during talks.
From Waverley Bridge to Lothian Road, the street was barricaded by traffic cones, forcing buses and taxis along George Street.
A source close to the council said Transport Initiatives Edinburgh (TIE), the branch of the council in charge of the tram works, would not bow to the contractors' demands.
He said: "What is the point of having a signed contract and an agreed budget and then paying more? Does that mean if there is a new contract, in six months they will want more money?"
He insisted that other companies could finish the tram work project.
He said: "We are aware that there are other contractors in the UK who would be available to continue the work. It's not something that's going to happen this month or next month, but clearly if you continue not to reach any resolution it's something that has to be looked at."
Scottish Tory chief whip David McLetchie yesterday handed out 2,000 leaflets on Princes Street urging the council not to be "held for ransom" by Bilfinger Berger. He said:
"It's going to be a significant delay. We have got to pull out all the legal stops to make sure that the contract we have is honoured."
A spokesman for Bilfinger Berger said: "As the client failed to meet contractually agreed conditions, and as no agreement has been reached, construction work in Princes Street cannot yet commence.
"Contrary to reports, additional costs of 80m have never been requested as a pre-condition for the start of works in Princes Street."
- Broken Rangers: Club signals intention to go into administration
- Rangers run into the ground as furious HRMC battles to claw back tax
- Scottish independence: David Cameron set to snub Alex Salmond’s separation talks bid
- Rangers blame HMRC for driving club to brink of administration
- Six Nations: Steadman given notice as ruthless Robinson seeks to strengthen team
- Scottish independence: No breakthrough in talks between Alex Salmond and Michael Moore
- Scottish independence: David Cameron set to snub Alex Salmond’s separation talks bid
- The Rumour Mill: Tuesday’s football news and gossip
- The Rumour Mill: Monday’s football news and gossip
- Alex Salmond claims Scottish independence would be good for English regions
Looking for...
Featured advertisers
Jobs
Search for a job
Motors
Search for a car
Property
Search for a house
Weather for Edinburgh
Wednesday 15 February 2012
Today
Cloudy
Temperature: 6 C to 11 C
Wind Speed: 18 mph
Wind direction: West
Tomorrow
Cloudy
Temperature: 6 C to 11 C
Wind Speed: 20 mph
Wind direction: South west